Stonne Construction was tasked with the demolition of Edison High School. Our responsibilities included clearing the site of debris and processing the building’s stone into 2A modified, 3″, and 4″ ballast. We strategically used the recycled 2A material for controlled basement backfills, ensuring 100% compaction. Following debris removal, we meticulously graded the site to subgrade in preparation for the upcoming construction.
Edison Square (Edison High School Demolition)

Client
Leslie Smallwood, Mosaic Development Partners
Location
7th & Lehigh Streets, Philadelphia, PA
Start Date
July 1, 2012
End Date
January 31, 2013
Awarding Organization
Mosaic Development Partners/Orens Brothers Real Estate Inc.